What is testing, adjusting and balancing (TAB)?

Testing, adjusting and balancing (TAB) is the process of measuring the air and water flows in an HVAC system and adjusting dampers, valves and fan or pump settings until each outlet and coil gets its design flow. It has two parts, air balancing and chilled water balancing, and ends with a report of design against measured values.

Reviewed by the MSTECK engineering team · Updated

What TAB Covers

What TAB Covers: Air Side and Water Side

Most comfort complaints come down to flow. TAB finds where the air and water are going and sets the system to deliver what the design intended.

  • Air balancing: supply, return, fresh and exhaust air at every outlet, AHU, FAHU and FCU.
  • Chilled water balancing: flow through every coil, branch and riser.
  • Fans and pumps: duty, pressure and speed checked against design.
  • Fault isolation: separating airflow, hydronic and controls problems.
  • TAB reports: for consultants, authorities and facilities teams.

Why Choose MSTECK for TAB

  • Procedures to ASHRAE 111, NEBB and CIBSE Codes A and W
  • Calibrated instruments, certificates included
  • We can fix what TAB finds, including live valve replacement

Get a TAB Quote

An engineer reviews every request and replies with an approach and a quote.

Please enter your name.
Please enter your phone number.
Please enter your email address.
Please tell us briefly what you need.

By sending this form you agree to our Privacy Policy.

Prefer to message us directly?

How We Work

How a TAB Job Runs

  1. Review the design. Drawings, design flows and equipment data.
  2. Prepare. The system is checked so it is ready to balance.
  3. Measure. Air and water flows, pressures and temperatures.
  4. Adjust. Dampers, valves and fan or pump settings set to design.
  5. Verify and report. Everything re-measured and recorded in the TAB report.

What Goes in the TAB Report

  • Design and measured flow for every terminal, coil and valve, with the percentage of design
  • Final settings of dampers, balancing valves, PICVs and fan or pump speeds
  • Fan and pump data duty, pressure, speed and motor current against design
  • Instrument list with serial numbers and calibration dates
  • Issues found such as blocked strainers, missing valves or undersized ducts, with recommendations
Instruments and Standards

How We Measure

  • Capture hood (flow hood) for supply and extract air at diffusers and grilles
  • Digital micromanometer with pitot tube for duct traverses and fan pressures
  • Thermal and vane anemometers for face velocities at coils, louvres and openings
  • Balancing valve manometer for flow through commissioning valves and PICVs
  • Ultrasonic clamp-on flow meter for chilled water flow where no valve can be read
  • Thermometers, hygrometer and tachometer for temperatures, humidity and fan or motor speed

Standards We Work To

  • ASHRAE Standard 111 for measurement, testing, adjusting and balancing
  • NEBB procedural standards for TAB
  • CIBSE Commissioning Codes A (air) and W (water) where specified
  • Or the consultant's specification and tolerances, where these differ

Every instrument is in calibration, and the certificates go in the report.

Questions

Frequently Asked Questions

What is the difference between air balancing and water balancing?

Air balancing sets the airflow at every fan, duct and outlet. Water balancing sets the chilled water flow through every coil and branch. Most systems need both.

Do you provide TAB reports for handover?

Yes. The report records design and measured values for consultants, authorities and facilities teams.

Can TAB fix a system that was never balanced?

Often, yes. Many underperforming systems were never properly balanced. Where TAB finds a design or equipment fault, we tell you what fixing it involves.

Which standards do you follow?

ASHRAE Standard 111, NEBB procedural standards, or CIBSE Commissioning Codes A and W, or your specification where it differs.

Which areas do you cover?

Projects across the UAE, including Dubai, Sharjah, Ajman and Abu Dhabi, run from our office in Al Qusais Industrial Area 5, Dubai.

Get a Quote for Your Project

Pipe size, system, location in the building and when it needs doing. Photos help. An engineer replies with an approach and a price.